With €45.00 of set-up and €2.00 per part, one piece costs €47.00 (24 × the part itself), ten cost €6.50 each and a hundred €2.45 each. From 225 parts the set-up adds less than 10 % to the price.
Price per part by batch size
| Quantity | Price per part | Set-up per part | Set-up's share |
|---|---|---|---|
| 1 | €47.00 | €45.00 | 96 % |
| 2 | €24.50 | €22.50 | 92 % |
| 5 | €11.00 | €9.00 | 82 % |
| 10 | €6.50 | €4.50 | 69 % |
| 25 | €3.80 | €1.80 | 47 % |
| 50 | €2.90 | €0.90 | 31 % |
| 100 | €2.45 | €0.45 | 18 % |
| 250 | €2.18 | €0.18 | 8 % |
| 1,000 | €2.04 | €0.04 | 2 % |
€45.00 of set-up on a part costing €2.00.
How it's calculated
Every job has a cost that doesn't depend on the quantity: loading a sheet and running the program, setting up the press brake, clamping a welding jig, programming. Spread over the batch it is:
price per part = cost per part + set-up ÷ quantityset-up's share = (set-up ÷ quantity) ÷ price per partbatch for a share s = set-up ÷ (cost per part × s)
The curve is steep at first and flat later: going from 1 to 10 parts cuts the set-up per part by nine tenths; going from 100 to 1,000 hardly changes the price. With €45.00 of set-up and a part costing €2.00, one piece costs €47.00, but from 225 pieces the set-up adds less than 10 % and from 450 less than 5 %.
What counts as set-up in a sheet metal shop:
- Laser: loading the sheet, the program, the first-part check, per sheet (about 5 minutes); larger batches share it across more parts on more sheets.
- Press brake: tools, back gauge and a first part with the angles checked, per order line (15 to 30 minutes).
- Welding: reading the drawing and building the jig, per order line.
- Office: quoting, the order, the invoice. Often forgotten, and for small orders the biggest set-up of all.
That's why shops charge minimum order values and why customers get better prices for bigger batches. CadQuoter prices both automatically: the set-up per sheet and per line from the shop's settings, quantity discounts on top, and a minimum order value, while the office set-up drops to nearly nothing because the customer quotes and orders online.
Worked example
A part costs €2.00 to make; the set-up (one sheet loaded and the press brake set up) is €45.00:
- 1 part: €47.00
- 10 parts: €6.50 each
- 100 parts: €2.45 each
- The set-up drops below 10 % of the price at 225 parts
Do this for every part automatically
CadQuoter reads your customers' STEP, DXF and DWG files and prices laser cutting, bending, welding and tube cutting with your machines, sheets and rates, in seconds. Customers order and pay online; you get the order with the flat patterns.
The demo needs no account. 200 PLN / €50 + VAT per month, no commission.
Frequently asked questions
How do I spread set-up costs over a batch?
Divide the set-up by the quantity and add it to the cost of each part. The calculator shows how the price per part falls with the batch size.
What batch size makes the set-up negligible?
Set-up ÷ (cost per part × the share you accept). For a 10 % share, €45.00 of set-up and €2.00 per part: 225 parts.
Should I charge a minimum order value?
For small orders, yes: the office time of quoting and invoicing is a set-up too. Many shops set it near one hour of machine time.
Do quantity discounts follow from this?
Partly: the set-up per part falls with the quantity by itself. A discount on top shares the efficiency of long runs with the customer.